英语人>网络例句>sub contractor 相关的网络例句
sub contractor相关的网络例句

查询词典 sub contractor

与 sub contractor 相关的网络例句 [注:此内容来源于网络,仅供参考]

Variations 52.3 Exceeding 15 Percent If, on the issue of the Taking-Over Certificate for the whole of the Works, it is found that as a result of: all varied work valued under Sub-Clause 52.1 and 52.2, and all adjustments upon measurement of the estimated quantities set out in the Bill of Quantities, excluding Provisional Sums, daywork and adjustments of price made under Clause 70, But not from any other cause, there have been additions to or deductions from the Contract Price which taken together are in excess of 15 per cent of the "Effective Contract Price"(which for the purposes of this Sub-Clause shall mean the Contract Price excluding Provisional Sums, and allowance for dayworks, if any) then and in such event (subject to Any action already taken under any other Sub-Clause of this Clause), after due consultation by the Engineer with the Employer and the Contractor, there shall be added to or deducted from the Contract Price such further further sum as may be agreed between the Contractor and the Engineer or, failing agreement, determined by the Engineer having regard to the Contractor's Site and general overhead costs of the Contract.

如果在签发整个工程接收证书时,发现由于: 47 超过百分之 52.3 十五(15%)的变更所有按第52.1款和52.2款规定作价的全部变更工程;对工程量清单中开列的估算数量进行计量所做的全部调整费用,但不包括所有暂定金额,计日工作费用及按本文第 70 条规定所作的价格调整。而并非由于任何其他原因,当加到或从合同价中减去的金额总和超过了有效合同价格就本款而言,应指不包括暂定金额和计日工(如有的话的合同价的 15%时,那么,工程师应在与承包人和业主协商后,在考虑据本款采取的任何步骤后,再将合同价减少或增加一笔工程师与承包人协商的调整金额,若不能达成一致意见,则由工程师考虑承包人的现场管理费用及总管理费开文后确定此数额。

The Contractor does not receive the amount due under an Interim Payment Certificate within 42 days after the expiry of the time stated in Sub-Clause 14.7 within which payment is to be made except for deductions in accordance with Sub-Clause 2.5

在第14.7款规定的支付时间期满后42天内,承包商没有收到按开具的期中支付证书应向其支付的应付款额根据第2.5款(雇主的索赔进行扣除的金额除外

The reasonable cost of removal of Constructional Plant under sub-clause(7)of this Clause and,if required by the Contractor,return thereof the Contractor's main plant yard in his country of registration or to other destination,at no greater cost.

本条第7款所规定的搬迁建筑设备的合理费用,如果承包人要求,包括将此设备运回到承包人注册国的主要设备堆置场的费用,或运至其他地点的费用,但此费用不得超过运回注册国的费用。

EThe reasonable cost of removal of Constructional Plant under sub-clause (7) of this Clause and, if required by the Contractor, return thereof the Contractor's main plant yard in his country of registration or to other destination, at no greater cost.

本条第7款所规定的搬迁建筑设备的合理费用,如果承包人要求,包括将此设备运回到承包人注册国的主要设备堆置场的费用,或运至其他地点的费用,但此费用不得超过运回注册国的费用。

The reasonable cost of removal of Constructional Plant under sub-clause(7)of this Clause and,if required by the Contractor,return thereof the Contractors main plant yard in his country of registration or to other destination,at no greater cost.

本条第7款所规定的搬迁建筑设备的合理费用,如果承包人要求,包括将此设备运回到承包人注册国的主要设备堆置场的费用,或运至其他地点的费用,但此费用不得超过运回注册国的费用。

The contract, the contractor may, within the period of the contract, sub-contract the lands, mountains, grasslands, unreclaimed lands, beaches and water surfaces he has contracted for, and may also transfer the rights and duties agreed upon in the agricultural ''.

在承包期内,经发包方同意,承包方可以转包所承包的土地、山岭、草原、荒地、滩涂、水面,也可以将农业承包合同的权利和义务转让给第三者。

If, within the said time, such permission is noy granted, the Contractor may, but is not bound to, elect to treat the suspension where it affects part only of the Works, as an omission of such part under Clause 51 by giving a further notice to the Engineer to that effect, or where it affects the whole of the Works, treat the suspension as an event of default by the Employer and terminate his employment under the Contract in accordance with the Provisions of Sub-Clause 69.1, whereupon the provisions of Sub-Clause 69.2 and 69.3 shall apply.

如果在该期限内未得此项准许,则承包人可以根据第 51 条规定,向工程师递送通知,将仅影响该工程局部的停工工程视为被取消部分不予施工,或者,当在此项停工影响整个工程施工时,则可视为业主违约。,并据第 69.1 款终止合同,在这种情况发生时,应接第 69.2 款及第 69.3 款处理。

C subcontracting any part of the work to the sub-contractor who has been designated in the contract.

合同中已被指定的分包商对工程的任何一部分进行分包。

If any payment is made by the Carrier to the Merchant in respect of any claim arising from the combined transport carriage, the Carrier shall be automatically subrogated to or given all rights of the Merchant against all others including pre-carrier or on-carrier or Sub-contractor on account of such loss or damage.

如果承运人已就因联合运输而引起的任何索赔向货方支付任何款项,承运人便应自然而然地以代位关系而取得或被赋予货方针对所有其他人包括前一程承运人或续程承运人或分立契约人就此项灭失或损害而享有的权利。

But there is room for the law to be more specific in defining duties for the sub-contractor beyond broad generalisations.

法例在界定广义归纳范围以外的分判商的职责方面可更具体化。

第2/3页 首页 < 1 2 3 > 尾页
推荐网络例句

I'm strongly against the death penalty — it's an eye for an eye.

我不赞成死刑——这是以牙还牙的报复行为。

And to get you the support you need, we're enlisting all elements of our national power: our diplomacy and development, our economic might and our moral suasion, so that you and the rest of our military do not bear the burden of our security alone.

并给你们所须的支援,我们正徵召国家所有各种的力量:我们的外交及发展,我们的经济力量与道德劝说,所以你们与其他军人不须要孤独地负起国家安全的责任。

Imagine yourself to be an actor in a play on the stage.

设想你自己是一个演员在舞台上表演。